I have a build
system that performs the following sequence using P4 tasks included with Ant
1.6.5:
- Get/reserve new
ChangeList number using p4change.
- Checkout product
buildID file using p4edit.
- Update buildID file
with new build number and ChangeList number from step 1.
- Run build
tasks.
- If build succeeds,
submit the buildID file changes using p4submit; else revert
the ChangeList reserved in step 1 using
p4revert.
So far this has
seemed to work for several months. Recently I noticed that the ChangeList number
that I reserved in step 1 is not the one that was used on the submit in step 5
above. This has caused me to have to manually change the file to get it in sync
with the correct ChangeList. When the problem happens, the actual ChangeList
number used will be 2 or three numbers higher than the one reserved in step 1.
Also, the original ChangeList is not present in the Perforce system.
We use this
information to identify build points. It is critical that it is accurate so that
we can properly identify changes that occur between each
build.
Question:
Is there a way to ensure that the ChangeList recorded in the buildID file is
the same one used to submit the change?
See attached Ant
module(sourceControlTasks.xml) containing the following build
tasks:
update.buildID:Gets a new ChangeList
number and uses it to checkout the buildID file. The buildID file is updated.
Calls revert.buildID if on error.
submit.buildID: Submits change using
ChangeList number saved from update.buildID. Calls
revert.buildID if on error.
revert.buildID: Reverts ChangeList
saved from update.buildID.
Thanks.....
Scott Lavender |
SCM Specialist | Visiprise | office:
770.619.4166 | www.visiprise.com
It is our company policy not to accept email of any data
controlled by the International Traffic in Arms Regulations (ITAR). Please
direct inquiries to ITAR visiprise.com">ITAR visiprise.com
for instructions and authorization to transmit such
data.
|